Cloud migration for enterprises: phasing, dependencies and risks

An enterprise migration succeeds through a good inventory, deliberate migration choices per application, phased execution and a fallback plan.

Door de redactie van ClouwinoGepubliceerd Laatst bijgewerkt

Short answer

An enterprise cloud migration proceeds in phases: take inventory, map dependencies, choose a strategy per application, run pilots and cut over in a controlled way. The biggest risks are unknown connections, missing fallback plans and underestimated management effort.

Who is it for: Programme managers, architects and operational teams preparing a migration of a large application landscape.

Where do you start: inventory and dependencies

Many problems arise from what was not known. Map applications, databases, connections, batch jobs, licences and owners. Also watch for dependencies that nobody remembers, such as fixed addresses, shared file shares or outdated authentication.

Group applications that need to move together. An application with a slow connection to its database often performs poorly after the move if only one of the two sides migrates.

Which migration strategies exist?

Not every application gets the same treatment. Choose per application based on value, technology and remaining lifespan.

How do you carry out the migration in phases?

Start with a low-risk pilot to test the way of working, network, security and management. Learn from it before you scale up. Plan waves based on dependencies and the business rhythm, and avoid migrations in busy periods.

  1. Set up the base environment: network, identities, logging and policy.
  2. Run a pilot with a representative but not business-critical application.
  3. Migrate in waves and test functionally, on performance and on security.
  4. Cut over at an agreed moment with a fallback plan practised in advance.
  5. Keep the old environment available until the new one is stable, and then clean up in a controlled way.

Which risks do you need to monitor?

Examples are data loss or corruption during transfer, too long an interruption during the cutover, performance loss due to extra latency and security gaps from hasty configuration. There are organisational risks too: management teams need to learn new skills, and cost models work differently from those in your own data centre.

Risk and control measure

Common risks in large migrations.
RiskCauseControl measure
Unknown dependencyMissing documentationAnalyse network traffic and question owners
Long interruptionA lot of data or a complex cutoverPre-synchronise and practise the cutover
Performance lossExtra distance between componentsMigrate connected components together and measure
Security gapHasty or deviating configurationFixed templates, review and automated checks
Cost overrunUnderestimated usage or overcapacityCost monitoring and budget alerts from day one

Who is it not ideal for?

Frequently asked questions

When is a fallback plan really usable?

When it has been practised, the old environment is still up to date and it has been agreed in advance at which criteria you switch back.

How do you involve users?

Inform them early about interruptions, let key users test along and set up a clear reporting point for the first weeks.

What do you do with data that may not move?

Keep it in its own environment or region and design a secured connection. Record why and for how long this applies.